Inspection and Re-application of Sealant for External Wall and Cladding at PolyU West Kowloon Campus

2022年 9月 27日 - 10月 28日

**只提供英文版本**

 

Inspection and Re-application of Sealant for External Wall and Cladding at PolyU West Kowloon Campus

 

We wish to draw your attention to the following inspection and re-application work that has been scheduled to carry out from 7 October 2022 to 28 October 2022 on PolyU West Kowloon Campus:

 

Location

Description of Works

Affected Period

Affected Area

Remarks

PolyU West Kowloon Campus

To carry out and re-application of sealant for external wall and cladding

7 October 2022

(Friday)

to

28 October 2022

(Friday)

  • Designated areas from LG/F to R/F of the building.

 

 

  • Please close the window/s in your office during the course of work;
  • Gondola works will be conducted during the course of work.
  • Scaffolding will be erected at the external wall; and
  • Noise and dust will be generated during the course of work.

 

For enquiries, please contact CFM Helpdesk at 3746 0999 (WK Campus).

 

We would be grateful if you could also draw the above to the attention of your staff, students or visitors who may be affected.

 

Any inconvenience thus caused is much regretted.

 

Campus Facilities Management Office